Boiler house

Heat recovery systems

2.8.3

Safety information

Your attention is drawn to Safety Information sheet IM-GCM-10 as well as to any national or regional regulations concerning boiler blowdown.

In the UK guidance is given in HSE Guidance Note PM60.

General information

This information describes the Spirax Sarco heat recovery system which is designed to recover the heat in discharged boiler water from

automatic TDS control systems, and a proportion of this water in the form of flash steam. The heat recovery system must only be used to

recover heat from the TDS blowdown. There will be another blowdown point on the bottom of the boiler used for the intermittent removal of

precipitates. This should be kept entirely separate from the heat recovery system. Refer to separate literature for system selection details.

This equipment is designed to save energy. All pipework and the flash vessel should be lagged.

Installation

Flash vessel

As water passes through the blowdown valve it is reduced in pressure. Flash steam is formed and the pipework downstream of the valve will

contain a mixture of steam and blowdown water travelling at high velocity. If the pipeline to the flash vessel is too small in diameter the result

may be erosion of the pipework with turbulence and carryover as it enters the flash vessel.

The best arrangement is to increase the size of the pipework after the blowdown valve:

- Install the flash vessel at a high level adjacent but not bolted to the feedtank.

- Fit the pressure gauge set, safety valve and vacuum breaker as shown in Figure 2.

- Pipework from the flash vessel to the feedtank should match the vessel’s vent size.

- The safety valve should always be fitted with the centreline of the spring housing vertically above the valve.

- The discharge pipework must be installed so that undue stresses are not imposed upon the safety valve that could cause distortion and

leakage.

- Discharge pipework should be as short and straight as possible and discharge where it can not cause damage or injury to property or persons.

Discharge pipework must not be smaller in diameter than the valve outlet. Where it is necessary to install discharge pipework over a long

distance lowering of the performance and possible chatter can be avoided by fitting larger diameter pipe.

- There must be no shut-off device on the inlet or outlet of the safety valve.

- The size of pipework to drain should match the flash vessel drain connection size.

- The vacuum breaker must be installed in a vertical position above the flash vessel in the flash steam line to prevent a vacuum forming when

the blowdown valve shuts off.

Vacuum breaker

Pressure gauge,

gauge cock

and

'U' syphon

Flash steam

to feedtank

Safety valve fitted

on a full bore

swept bend.

Discharge piped

to a safe area.

Auto TDS

blowdown

inlet

1 m (max.)

2 m (min.)

Fig. 2 Flash vessel

Float trap

Residual blowdown

to drain

Drain valve

piped to open drain

Fig. 3 Example showing two float traps in parallel when

capacity demands

The build up of water in the flash vessel must be avoided so a float trap with continuous drainage of condensate at saturation temperature is

essential. The trap must be fitted so that the float arm rises and falls vertically with the direction of flow as indicated on the body. Where capacity

demands two float traps should be fitted in parallel (see Figure 3). The flowrate of residual blowdown through the trap is dependent on the head

of water above it. For the full rated capacity of the system the trap should be positioned at least 2 m below the flash vessel as shown in Figure 3.

It is usually most convenient to fit the trap at a low level for easy access immediately above the heat exchanger. No more than 1 m of horizontal

pipework should be used between the flash vessel and the float trap inlet to prevent the float trap from becoming steam locked.

Boiler Blowdown Heat Recovery Systems -

AI-P404-07 AB Issue 7

Installation, Operation and Maintenance

Page 2 of 4