Pipeline ancillaries

Separators and insulation jackets

Dimensions/mass (approximate) in mm and kg

IJ-S5 and IJ-S6

Safety information

Before placing or removing the insulation jacket, check if the

separator is in service. If it is, the metal surface will be hot enough

to burn and suitable protective clothing (e.g. gloves) should

be worn.

Handling

When the jacket is new, the insulation material is fully enclosed

within the inner and outer face and retained by the stitching. In this

condition, for handling, no special protective clothing is required.

However, if the inner and outer face become unstitched or damaged

so as to expose the insulation material, suitable protective clothing

(e.g. gloves, safety glasses, face mask and overalls) should be

worn.

Installation

Once the separator has been installed, the insulation jacket can

be fitted as follows:

IJ-S5 and IJ-S6

Place the jacket centrally on the left hand side of the separator.

Undo the middle velcro flap, slide the jacket down over the flanged

/threaded connection and pull velcro flap into secure position. Wrap

front and back of jacket around separator and secure fully by using

the top and bottom velcro flaps. Finally, pull and tie the top and

bottom drawcords to minimise any gaps that would allow air to

flow through or allow ingress of water.

IJ-S5-H and IJ-S6-H

Place the jacket centrally on the left hand side of the separator.

Undo the middle buckle straps, slide the jacket down over the

flanged/threaded connection and pull the buckle straps into secure

position. Wrap front and back of jacket around separator and

secure fully by using the top and bottom buckle straps. Finally, pull

and tie the top and bottom drawcords to minimise any gaps that

would allow air to flow through or allow ingress of water.

Flange insulation jackets

The separator insulation jacket should be fitted before any flange

insulation jackets.

Important note: Both the inner/outer face and insulation are

made with a bonded aluminium foil. At a temperature of 120°C the

adhesive bonding and the aluminium foil will start to degrade and

delamination of the foil will occur at between 150°C to 170°C.

Scorching of the internal fabric may occur at 150°C. Neither of

these reactions will impair the performance.

Disposal

This product is not recyclable and is non-combustible. For disposal

purposes consider the product to be mineral fibre and dispose of

in accordance with local regulations.

Size

DN15 and DN20

A

B

508

508

711

686

762

838

Insulation Mass

thickness

50

0.90

50

1.64

50

2.42

dimensions of the jacket

IJ-S5

and

IJ-S6

115➤

Insulation

Mass

thickness

50

1.06

50

2.00

50

2.60

dimensions of the jacket

DN25 and DN32

DN40 and DN50

The diagram below shows the unfolded

B

IJ-S5-H and IJ-S6-H

Size

DN15 and DN20

A

A

B

508

736

788

508

686

838

DN25 and DN32

DN40 and DN50

The diagram below shows the unfolded

A

IJ-S5-H

B

and

IJ-S6-H

0239050/6

IJ-S5, IJ-S6, IJ-S5-H and IJ-S6-H Insulation Jackets for S5 and S6 Separators

TI-P138-01 ST Issue 6

7.8.28